Chapter III of the Court, Qilu Agile project profiles and project management elements
Project profile
Project Overview
Engineering design requirements
Construction Features
Project Management Unit Introction
Project Management Essentials
The design phase control points
The tender stage control points
The construction phase control points
Completion stage control points
Chapter IV Qilu Agile Project Cost Control Yuan
Implementation of the project cost control in the preparation phase
To develop cost control implementation plan
Organizational measures to determine the cost control
Determine the Project Management Process
The whole process of cost control to determine major work
Project cost control decision-making stage
Overview
Project Feasibility Study
The concept of the feasibility study
The preparation of feasibility study report
The contents of the feasibility study report
Investment Estimation
The concept of Investment Estimation
Investment Estimation of the basis and proceres for
Investment Estimation method of calculation
Project Economic Evaluation
The concept of economic evaluation
Economic Evaluation
Net Present Value Method
The project design phase cost control
Overview
Cost control the content of
Cost control measures
Cost Control Features
Project Cost Control in the tender stage
Overview
The preparation of pre-tender
The preparation of tender documents
Contracting approach and pricing models
Bid Opening Results
Contract
The implementation phase of the project cost control
Overview
The control of the core of the contract
Strict control of engineering change and economic Visas
Strict control of material usage and quality of materials
Project measurement and progress payments paid
Node Control
Phase of the project cost control settlement
Overview
Proceres
Control
Clearing the table to review the project finalized
热心网友 时间:2024-07-11 22:43